A National Dam Safety Authority (NDSA) team on Saturday inspected the Polavaram irrigation project to review safety measures during the construction.

The team, comprising Southern Zone Director R. Giridhar and Deputy Director B. Hemaditya, visited the project for the first time following directions from the Union Ministry of Jal Shakti. It inspected structures and met Andhra Pradesh Water Resources Department officials.

In a briefing at the project meeting hall, Superintending Engineer P. Ramachandra Rao explained the progress of components, completed works and ongoing construction to the team.

The officials inspected the spillway, Gap 1, Gap 2 and Earth cum Rock Fill (ECRF) dam sections. The team sought details of the safety measures adopted since construction began, instrumentation installed and data collected to assess condition and performance of the structures.

Mr. Ramachandra Rao explained the monitoring arrangements and functioning of the safety instruments. Officials said a Supervisory Control and Data Acquisition (SCADA) system was being established to collect data from sensors, meters, valves and other equipment.